Update for Feb. 24
Construction crews will begin cutting foundation this week for new water and sewage lines to Davidson Hall. This work is necessary since each of the elementary classrooms will be furnished with a sink.
Some leveling work at the construction site will also be taking place this week. Additionally, the roof contractors will be returning to complete some edging and other finishing work.