Update for March 27
Construction is continuing on Davidson Hall, and the good weather recently has certainly helped. Here are some specific tasks taking place currently:
- Plumbing: Plumbing inspections were completed and received a green tag this week. Plumbers finished backfilling the saw cut areas in the building on March 26.
- Concrete: New stairs to the entrance are being formed and ready to pour. If no weather delay, concrete will come very soon.
- Framing: Framing exterior walls will begin in the next couple of days.
- Electricity: Electricians are set to begin their work to coincide with the framing