Projects completed this week:

  • New stairs were poured for the front of the building.  These are now ADA compliant and much safer for our students, faculty, and parents.
  • Most of the exterior walls were framed and the beginning of the exterior sheeting has started.
  • Electrical work for the interior has begun.

Coming Up:

  • Completion of exterior sheeting
  • Ongoing electrical work
  • Interior framing to begin