Progress continues on the construction of Davidson Hall. Following are some projects that have been completed recently or are currently underway.

  • A new steel beam has been installed to allow us to remove poles that would have been in three rooms.
  • Interior framing will be completed this week.
  • We have passed inspection on plumbing and electrical.
  • The installation of the fire sprinkler system has begun.
  • Exterior work will begin by pouring the footing for new exterior facing.
  • Windows have been installed.