Update for October 12, 2020
Work on Davidson Hall has been moving quickly in the past few weeks. The fencing around the perimeter has come down as crews shift more to indoor work. Here are some projects going on this week:
· Painters will continue applying first coat of paint this week.
· Roofers are finishing the new roof on the portion of the building that used to house the rifle range (see photos).
· Tile is almost complete in the girls and boys bathrooms (see photos)
· Oak material for furr downs and reception area has been received.
· Quote on HVAC was anticipated by today.
Some projects slated for next week include the following:
· Installation of oak, interior doors, windows, and grid ceiling will begin on Wednesday or Thursday.
· Painting will be going until sometime Tuesday or Wednesday.
· HVAC will get in early next week to install the flex duct in furr downs and offices (where not already installed).
· Trying to get demolition started on Monday on the retaining wall.